Maintenance at Dayton and Second begins March 30

Posted

Snohomish County PUD crews are scheduled to perform critical maintenance repair work at the intersection of Dayton Street and Second Avenue South, with overnight outages beginning March 30

 Power will be taken offline in the area beginning at 9 p.m., March 30-April 2, and restored the following morning by 5 a.m.

Dayton between Sunset Avenue and Second will be closed intermittently to replace a power pole and critical underground equipment.

Nearby residents may hear noise as work on the project is completed. The PUD said it will take all reasonable measures possible to reduce noise throughout the duration of the work. Any residents and/or property owners who will lose power will be notified directly by PUD staff.

For more information, call PUD Engineer Andy Tran at 425-359-1123.